Check NOTAMS to makes sure construction starts on the schedule posted below. I will update if there are changes.

Work will begin on Monday, May 22. The first half of the project is a full length rehabilitation of the entire taxiway system. The taxiway work will be divided into three phases. Phase #1: A - 8 to just south of A -5. Phase #2: From Just south of A-5 to just south of A-3, leaving the majority of hangars accessible from the northern access to ā€œDā€ ramp. Phase #3: Just south of A-3 to A-1.

The second half of this project includes crack sealing, sealcoating, and remarking of runway 03/21. This requires a runway closure. The closure is scheduled for June 5-14. Helicopter operations will be allowed to continue.